/sla) is the primary operational health dashboard. It gives you an immediate picture of which productions are progressing well and which need attention — across all active companies and projects.
Summary cards
At the top of the page, four summary cards give a quick snapshot:| Card | Description |
|---|---|
| Active Plans | Total number of non-finished production plans |
| Overdue | Plans that have been in their current stage for 7 or more days |
| At Risk | Plans in stage for 3–6 days |
| On Track | Plans in stage for fewer than 3 days |
Stage bar chart
Below the summary cards, a bar chart shows the average days per pipeline stage across all active plans. Bars are colour-coded by SLA severity:- Emerald (green) — average is under 3 days (On Track)
- Amber — average is 3–6 days (At Risk)
- Red — average is 7 or more days (Overdue)
Bottleneck table
The main section of the page is a collapsible tree table, sorted worst-first (most overdue at the top). The hierarchy is:- The current pipeline stage (with an inline dropdown to change it)
- The SLA badge — On Track / At Risk / Overdue with the number of days
- The COps and POC assignees
Filters
Company status tabs
Filter the company list at the top of the tree using the tabs:- Active — active client companies only
- Starred — priority/starred companies only
- Demo — demo companies only